Projects By StakeholderStakeholder | Project Name | Project Status | Timeframe | Project Description |
---|---|---|---|---|
Air Force Reserve Command | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
City of Niles | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
City of Niles Engineer | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
City of Niles Public Safety Department | ||||
Municipal Computer Aided Dispatch to Emergency Vehicles | Planned | Long | Integrating the computer aided dispatch to the emergency management center that will allow the operators to dispatch emergency response vehicles to the scene more rapidly. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
City of Warren Operations Department | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
Trumbull County - The North River Road / Elm Road Safety Enhancement Project | Planned | Short | This project will consist of constructing a skid resistant surface course, upgrading pavement markings, improving traffic lane alignments, and upgrading the existing traffic signals to optimize traffic timing and flow. Access management will also be con | |
City of Warren Public Service and Safety Department | ||||
Municipal Computer Aided Dispatch to Emergency Vehicles | Planned | Long | Integrating the computer aided dispatch to the emergency management center that will allow the operators to dispatch emergency response vehicles to the scene more rapidly. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
City of Youngstown | ||||
Municipal Computer Aided Dispatch to Emergency Vehicles | Planned | Long | Integrating the computer aided dispatch to the emergency management center that will allow the operators to dispatch emergency response vehicles to the scene more rapidly. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
City of Youngstown Street Department | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
WRTA Bus Traffic Signal Priority | Planned | Medium | Study key transit corridors for applicability of bus traffic signal priority to improve transit travel time. Implement transit signal priority on traffic signals on identified corridors. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
Commercial Fleet Owners | ||||
Mahoning / Trumbull Counties Commercial Vehicle Operations | Planned | Long | System collecting data carried in trucks traveling on specific routes. | |
County Sheriff | ||||
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Financial Institutions | ||||
WRTA Passenger Management System | Planned | Short | System that provides fare reconciliation between peer agencies using a common travel card. | |
General Public | ||||
Connected Vehicle | Planned | Long | Deployment of Connected Vehicle infrastructure, including roadside equipment and controller modifications, to implement vehicle-to-infrastructure (V2I) communications in the 2014-2020 timeframe (as vehicles are equipped). Connected Vehicle is a suite of t | |
ODOT Traveler Information Delivery Methods | Planned | Medium | Implement traveler information dissemination methods which may include personalized traveler information on a subscription basis delivered to cell phones, pagers, personal computing devices. Information gathered through various detection methods could als | |
Mahoning County | ||||
Mahoning / Trumbull Counties Commercial Vehicle Operations | Planned | Long | System collecting data carried in trucks traveling on specific routes. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
Mahoning County Emergency Management Agency | ||||
ODOT Install Snow and Ice Detection Management and Advanced Snow Plow Systems | Planned | Long | Road weather information systems integrated with advanced technology snow plows. These systems provide early warning of icing and snow, and meter the amount of chemical and/or sand applied based on surface conditions, including amount of chemicals already | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
Mahoning County Traffic Department | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
Niles-Trumbull Transit System (NiTTS) | ||||
NiTTS AVL System | Planned | Medium | Installation of AVL on all NiTTS vehicles. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
NiTTS Google Transit | Planned | Short | NiTTS will pair with Google to feed information on Google transit. | |
ODOT | ||||
Connected Vehicle | Planned | Long | Deployment of Connected Vehicle infrastructure, including roadside equipment and controller modifications, to implement vehicle-to-infrastructure (V2I) communications in the 2014-2020 timeframe (as vehicles are equipped). Connected Vehicle is a suite of t | |
Connection of Private Providers | Planned | Long | Private providers to work with ODOT to establish links with private providers to deliver traffic information to more people in different facets. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
ODOT Highway-Rail Intersection Advanced Safety Systems | Planned | Long | Install advanced Highway-Rail Safety Systems at key crossings. A study must be conducted to identify the crossings and the preferred system. | |
ODOT Install Snow and Ice Detection Management and Advanced Snow Plow Systems | Planned | Long | Road weather information systems integrated with advanced technology snow plows. These systems provide early warning of icing and snow, and meter the amount of chemical and/or sand applied based on surface conditions, including amount of chemicals already | |
ODOT Maintenance Vehicle Upgrade | Planned | Long | Automatic Vehicle Location for maintenance vehicles. | |
ODOT Service Patrols | Planned | Medium | Purchase and operate one freeway service patrol vehicle. | |
ODOT Traveler Information Delivery Methods | Planned | Medium | Implement traveler information dissemination methods which may include personalized traveler information on a subscription basis delivered to cell phones, pagers, personal computing devices. Information gathered through various detection methods could als | |
ODOT Work Zone Safety Improvements | Planned | Medium | Improvements to work zones to reduce collisions. Ability to alert drivers of a construction zone, roadway hazard, or speed change. | |
YSU Research Program: Work Zones | Planned | Medium | Establish a research program, in conjunction with ODOT, to test new implementation concepts such as crash mitigation or work zone operations systems. | |
YSU Research Program: Real-Time Stress Monitoring of Highway Bridges | Planned | Short | This collaborative research aims to develop a real-time stress monitoring system for highway bridges with a secured wireless sensor network. The program monitors the stress of highway bridges in Mahoning County with a light-weight and reliable wireless se | |
Ohio State Highway Patrol (OSHP) | ||||
ODOT Install Snow and Ice Detection Management and Advanced Snow Plow Systems | Planned | Long | Road weather information systems integrated with advanced technology snow plows. These systems provide early warning of icing and snow, and meter the amount of chemical and/or sand applied based on surface conditions, including amount of chemicals already | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
Other Municipalities and Townships | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
Municipal Computer Aided Dispatch to Emergency Vehicles | Planned | Long | Integrating the computer aided dispatch to the emergency management center that will allow the operators to dispatch emergency response vehicles to the scene more rapidly. | |
City of Newton Falls Signal Pre-emption | Planned | Short | Pre-emption will be provided on all approaches for four signalized intersections including W. Broad at Ridge/Windham, W. Broad at Canal, Broad at Center, and E. Broad at Milton. Seventeen emergency vehicles, including fire, EMS, and police, will be retro | |
Trumbull County - Warren Sharon Road/Howland Wislon Road Intersection Project | Planned | Short | This intersection improvement project will consist of a signal improvement and the addition of left turn lanes at the intersection of Warren Sharon Road and Howland Wilson Road in Howland Township. | |
Penn DOT | ||||
ODOT Install Snow and Ice Detection Management and Advanced Snow Plow Systems | Planned | Long | Road weather information systems integrated with advanced technology snow plows. These systems provide early warning of icing and snow, and meter the amount of chemical and/or sand applied based on surface conditions, including amount of chemicals already | |
Private Information Service Providers | ||||
NiTTS Google Transit | Planned | Short | NiTTS will pair with Google to feed information on Google transit. | |
Railroad Operators | ||||
ODOT Highway-Rail Intersection Advanced Safety Systems | Planned | Long | Install advanced Highway-Rail Safety Systems at key crossings. A study must be conducted to identify the crossings and the preferred system. | |
Social Networking Firms | ||||
Connection of Private Providers | Planned | Long | Private providers to work with ODOT to establish links with private providers to deliver traffic information to more people in different facets. | |
ODOT Traveler Information Delivery Methods | Planned | Medium | Implement traveler information dissemination methods which may include personalized traveler information on a subscription basis delivered to cell phones, pagers, personal computing devices. Information gathered through various detection methods could als | |
Trumbull County | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
Mahoning / Trumbull Counties Commercial Vehicle Operations | Planned | Long | System collecting data carried in trucks traveling on specific routes. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Trumbull County Maintenance Vehicle Upgrade | Planned | Medium | Automatic Vehicle Location for maintenance vehicles. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
Trumbull County - The North River Road / Elm Road Safety Enhancement Project | Planned | Short | This project will consist of constructing a skid resistant surface course, upgrading pavement markings, improving traffic lane alignments, and upgrading the existing traffic signals to optimize traffic timing and flow. Access management will also be con | |
Trumbull County - Warren Sharon Road/Howland Wislon Road Intersection Project | Planned | Short | This intersection improvement project will consist of a signal improvement and the addition of left turn lanes at the intersection of Warren Sharon Road and Howland Wilson Road in Howland Township. | |
Trumbull County Emergency Management | ||||
ODOT Install Snow and Ice Detection Management and Advanced Snow Plow Systems | Planned | Long | Road weather information systems integrated with advanced technology snow plows. These systems provide early warning of icing and snow, and meter the amount of chemical and/or sand applied based on surface conditions, including amount of chemicals already | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
Trumbull County Engineer | ||||
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 2 | Planned | Long | Signal upgrade and coordination along the major evacuation routes. | |
Municipal Signal Pre-Emption | Planned | Long | Pre-emption signal system for emergency vehicles | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
Trumbull County - The North River Road / Elm Road Safety Enhancement Project | Planned | Short | This project will consist of constructing a skid resistant surface course, upgrading pavement markings, improving traffic lane alignments, and upgrading the existing traffic signals to optimize traffic timing and flow. Access management will also be con | |
Trumbull County - Warren Sharon Road/Howland Wislon Road Intersection Project | Planned | Short | This intersection improvement project will consist of a signal improvement and the addition of left turn lanes at the intersection of Warren Sharon Road and Howland Wilson Road in Howland Township. | |
Western Reserve Transit Authority (WRTA) | ||||
ODOT Install Snow and Ice Detection Management and Advanced Snow Plow Systems | Planned | Long | Road weather information systems integrated with advanced technology snow plows. These systems provide early warning of icing and snow, and meter the amount of chemical and/or sand applied based on surface conditions, including amount of chemicals already | |
WRTA Bus Traffic Signal Priority | Planned | Medium | Study key transit corridors for applicability of bus traffic signal priority to improve transit travel time. Implement transit signal priority on traffic signals on identified corridors. | |
WRTA Kiosks at Transfer Points | Planned | Medium | WRTA to establish kiosk at key locations to provide bus route information and trip planning. | |
WRTA Surveillance Control | Planned | Medium | To include CCTV at certain locations to provide surveillance at stations and surrounding areas for security purposes. | |
Eastgate / County Signal System Upgrades and Evacuation Plan Updates - Part 1 | Planned | Short | Study and development of plan to evacuate Trumbull and Mahoning Counties in case of an emergency affecting mass area. | |
NiTTS Advanced Paratransit Scheduling and Dispatch System | Planned | Short | Implement an advanced para-transit scheduling and dispatch system at NiTTS coordinated with WRTA. | |
WRTA Passenger Management System | Planned | Short | System that provides fare reconciliation between peer agencies using a common travel card. | |
WRTA/NiTTS Transit Vehicle Updates | Planned | Short | Installation of Wireless Internet Feed on buses, automated signs, and annunciators. |