Description: This equipment package disseminates work activity schedules and current asset restrictions to other agencies. Work schedules are coordinated with operating agencies, factoring in the needs and activities of other agencies and adjacent jurisdictions. Work schedules are also distributed to Information Service Providers for dissemination to the traveling public.
Functional Requirements:
  1. The center shall provide work zone activities affecting the road network including the nature of the maintenance or construction activity, location, impact to the roadway, expected time(s) and duration of impact, anticipated delays, alternate routes, and suggested speed limits. This information may be augmented with images that provide a visual indication of current work zone status and traffic impacts.
  2. The center shall provide status information about scheduled maintenance and construction activities including anticipated closures and impact to the roadway, alternate routes, anticipated delays, closure times, and durations. The information is provided to other management centers such as traffic, emergency, transit, traveler information providers, other maintenance centers, multimodal transportation providers, rail operations, and the media.
  3. The center shall collect and respond to feedback concerning scheduled maintenance and construction activities with other management centers such as traffic, emergency, transit, and rail operations.
  4. The center shall collect and disseminate asset restriction information levied on transportation asset usage based on infrastructure design, surveys, tests, or analyses. This includes standard facility design height, width, and weight restrictions, special restrictions such as spring weight restrictions, and temporary facility restrictions that are imposed during maintenance and construction.
  5. The center shall exchange information with administrative systems to support the planning and scheduling of maintenance and construction activities. This information includes: equipment and consumables resupply purchase request status, personnel qualifications including training and special certifications, environmental regulations and rules that may impact maintenance activities, and requests and project requirements from contract administration.
  6. The center shall exchange rail schedules and work plans with rail operations centers.
Included In: HDOT-HWY-K Maintenance Dispatch
Kauai DPW Maintenance Dispatch
 

The Hawaiian language uses two diacritical markings. The 'okina is a glottal stop; and the kahako is a macron. The State of Hawaii strongly encourages the use of Hawaiian diacritical markings. The National ITS Architecture tool, Turbo Architecture, does not allow for the Hawaiian diacritical markings to be input and as such, customized service package diagrams, operational concepts and other outputs from Turbo are unable to reflect the diacritical markings. To ensure consistency in this ITS Architecture website, no Hawaiian diacritical markings will be used.